How Long a Kitchen Remodel Takes in South Florida: The 4–6 Week Schedule, Week by Week

Short answer: a typical Dreamery kitchen takes 4 to 6 weeks from signed contract to final walkthrough, and about two more weeks before that for the design and the quote. Structural changes, condo approvals and stone that has to be ordered can add time; the finish date is written into the contract either way. Here is where the weeks go.

Before the contract: about two weeks

Day 1 — consultation at your home. The designer measures, photographs, looks at the plumbing, the panel and the soffit, brings door and finish samples and talks through the layout. About 30 minutes.

Within 5 business days — 3D design and itemized quote. You see the kitchen in 3D and get one written price with every line on it. The written estimate is free; the 3D design package is $99 instead of the regular $500, and free when you sign the contract. Most clients take a few days to a week to decide on finishes and sign.

Weeks 1–3: your cabinets are built

This is the part that makes the schedule work. The day the contract is signed, our Coral Springs shop starts building the cabinets to your measurements; production typically takes one to three weeks. Because the cabinets are built locally rather than shipped from overseas or held in a distributor’s queue, your kitchen stays untouched until they are ready. Nobody lives with a demolished kitchen waiting for boxes to arrive.

Week 3–4: demolition and rough-in

Demolition takes one to two days. Then plumbing and electrical rough-in: new drain and supply positions for the sink and dishwasher, circuits for the island, range and lighting, exhaust for the hood. If a wall is coming out, the beam goes in now. Rough plumbing and electrical inspections are booked as each is reached — usually within the same week — and the walls are closed only after they pass.

Week 4–5: cabinets, then the countertop template

Cabinet installation takes two to four days for a typical kitchen: bases first, leveled and secured; then uppers; then panels, fillers, crown and hardware. As soon as the bases are set, the countertop is templated on the installed cabinets — never from a drawing — and the slab goes to fabrication. Fabrication typically takes about a week, which is the one stretch where the crew is not in your kitchen every day.

Week 5–6: countertops, backsplash, trim, final

Countertops are set and seamed, the sink is mounted and plumbed, the cooktop cut-out fitted. Backsplash tile follows the next day, then plumbing and electrical trim — faucet, disposal, dishwasher, outlets, lighting — paint touch-ups, and the final inspection. The last step is the walkthrough with you: every door, drawer and fixture checked, a punch list if anything needs it, and the final 10% payment only when it is closed.

What adds time — and how much

  • A load-bearing wall: engineered drawings and a beam — typically one to two extra weeks, mostly before demolition.
  • A condo: board approval before anything starts — commonly a few weeks — plus a longer install window inside posted work hours.
  • Natural stone or special-order quartz: slab availability can add a week or two; quartz from stock does not.
  • Appliances on back-order: we plan the cabinet openings around the exact models and can finish everything else while you wait, but the kitchen is not “done” until they are in.
  • Mid-project additions: priced in writing before they are done; large additions get a revised finish date in writing too.

What does not add time

Distance within South Florida: our crew works on the same day-by-day schedule in West Palm Beach or Miami as in Coral Springs. And material delays on cabinets, because there is no third-party factory in the chain.

Read what the same project costs in our kitchen cost guide.

Get a free in-home estimate

Share:

Book a free in-home estimate

We measure at your home and give you one written, itemized price, fixed before we start. Free, no obligation.

★ 4.9 · 56 client reviews · Own Factory · Family-Owned

What are you looking to remodel?

Pick one to continue.

Kitchen
Bathroom
Flooring
Whole Home
Other

When do you want to start?

This helps us plan the schedule.

⚡ASAP
📅1–3 months
🗓️3–6 months
🔍Just researching

Approximate budget?

We can help you review financing options if needed.

💵Under $10k
💰$10k–25k
💎$25k–50k
👑$50k+
🤔Not sure yet

What's your ZIP code?

We serve Miami-Dade, Broward, Palm Beach counties.

How can we reach you?

We'll call within 1 hour with a free, no-obligation estimate.

🔒 We use your details to respond to your request and never sell them. Privacy Policy
Kitchen & bath remodeling across South Florida: Aventura · Aventura bathrooms · Boca Raton · Boca Raton bathrooms · Boynton Beach · Boynton Beach bathrooms · Coral Gables · Coral Gables bathrooms · Coral Springs · Coral Springs bathrooms · Davie · Davie bathrooms · Delray Beach · Delray Beach bathrooms · Doral · Doral bathrooms · Fort Lauderdale · Fort Lauderdale bathrooms · Hialeah · Hialeah bathrooms · Hollywood · Hollywood bathrooms · Jupiter · Jupiter bathrooms · Kendall · Kendall bathrooms · Miami · Miami bathrooms · Miami Beach · Miami Beach bathrooms · Oakland Park · Oakland Park bathrooms · Parkland · Parkland bathrooms · Pembroke Pines · Pembroke Pines bathrooms · Pinecrest · Pinecrest bathrooms · Plantation · Plantation bathrooms · Pompano Beach · Pompano Beach bathrooms · Sunrise · Sunrise bathrooms · West Palm Beach · West Palm Beach bathrooms · Weston · Weston bathrooms
Service Areas — Miami-Dade, Broward & Palm BeachKitchen Remodeling  ·  Bathroom Remodeling  ·  Kitchen Remodeling Fort Lauderdale  ·  Kitchen Remodeling Miami  ·  Kitchen Remodeling Boca Raton  ·  Kitchen Remodeling Coral Springs  ·  Kitchen Remodeling Parkland  ·  Custom Kitchen Cabinets